Media Releases
Sycamore Street Road Closure
FOR IMMEDIATE RELEASE
 
August 30, 2017
 
Contact: Jonathan Ely
Staff Engineer
Engineering Division
479-444-3424
jely@fayetteville-ar.gov
 

Utility Work to Close Sections of Sycamore Street for Twelve Weeks
 
FAYETTEVILLE, Ark. — The City has approved a temporary road closure permit for utility work on several sections of Sycamore Street. Construction work will be conducted in three phases over a 12-week period from Thursday, August 31 through Wednesday, November 15, 2017. The road closures are from 7 a.m. through 7 p.m., six days a week (Monday – Saturday). Detours will be marked. Residents will be allowed access as needed. Steel plates and temporary concrete will cover the construction work during evenings and on Sundays.
 
The anticipated schedule is:
  1. Sycamore Street (College to Woodland): August 31 – September 30
  2. Sycamore Street (Green Valley to Woolsey): October 1 – November 1
  3. Sycamore Street (Woolsey to Gregg): November 1 – 14
 
Please use extreme caution when in the work area.
 
For more information about this project, please contact Paul Knopp with Black Hills Energy by telephone 479-582-7840 or email paul.knopp@blackhillscorp.com.
 
To view other road and lane closures or to sign up for notifications of closures, please visit this webpage.

###